Scheme Details
DISTRICT
Ghazipur
AGENCY
HFCL- JWIL (JV)
SCHEME ID
20088579
SCHEME NAME
NASIRPUR KHAS W/S SCHEME (HFCL)
ESTIMATED COST
279.15
EXPENDITURE
122.26
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
16135.00
Meter
Length Laid
15676.80
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Saidpur | Nasirpur Khas | 472143 | Nasirpur Khas | 189 | 184 | 97% | Work In Progress | Not Certified |
| 2 | Ghazipur | Saidpur | Nasirpur Khas | 472144 | Rasulpur | 3 | 1 | 33% | Work In Progress | Not Certified |
| 3 | Ghazipur | Saidpur | Nasirpur Khas | 472145 | Kirtupur | 33 | 30 | 91% | Work In Progress | Not Certified |
| 4 | Ghazipur | Saidpur | Nasirpur Khas | 472146 | Inrupur | 82 | 80 | 98% | Work In Progress | Not Certified |