Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Vindhya-GAJA (JV) | 20088673 | Kasampur Lekhraj & Kherijat Water Supply Scheme | 710.01 | 403.60 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 44 | 44 | Yes | 0 | NA | No | 19300.00 | 16898.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Netaur | Kherijat | 386846 | Kherijat | 172 | 172 | 100 | Har Gar Jal | Not Certified |
| 2 | Bijnor | Netaur | Kherijat | 386847 | Taharpur Tappa Nangla | 105 | 61 | 58 | Work In Progress | Not Certified |
| 3 | Bijnor | Netaur | Kherijat | 386848 | Mominpur Lalkunwar | 80 | 23 | 29 | Work In Progress | Not Certified |
| 4 | Bijnor | Netaur | Kherijat | 386849 | Mujaffarpur Devidas | 56 | 14 | 25 | Work In Progress | Not Certified |
| 5 | Bijnor | Netaur | Kherijat | 386850 | Darbarpur | 108 | 108 | 100 | Har Gar Jal | Not Certified |
| 6 | Bijnor | Netaur | Kasampur Lekhraj | 386879 | Kasampur Lekhraj | 253 | 253 | 100 | Har Gar Jal | Not Certified |
| 7 | Bijnor | Netaur | Kasampur Lekhraj | 386880 | Sadkabad | 127 | 89 | 70 | Work In Progress | Not Certified |