Scheme Details
DISTRICT
Auraiya
AGENCY
GVPR
SCHEME ID
20088687
SCHEME NAME
Ailchipur & Halepur &Tarwabiku
ESTIMATED COST
600.59
EXPENDITURE
375.90
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
36
Procured
36
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
17040.00
Meter
Length Laid
17081.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Ajitmal | Ailchinagar | 420611 | Ailchinagar | 241 | 241 | 100% | Har Ghar Jal | Certified |
| 2 | Auraiya | Ajitmal | Ailchinagar | 420612 | Atsu | 82 | 80 | 98% | Work In Progress | Not Certified |
| 3 | Auraiya | Ajitmal | Halepur | 420628 | Halepur | 303 | 297 | 98% | Work In Progress | Not Certified |
| 4 | Auraiya | Ajitmal | Tarwabiku | 420629 | Tarwabiku | 300 | 293 | 98% | Work In Progress | Not Certified |