Scheme Details
DISTRICT
Auraiya
AGENCY
GVPR
SCHEME ID
20088691
SCHEME NAME
Ali & Tilakpur sarmai PWS
ESTIMATED COST
664.84
EXPENDITURE
508.98
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
7
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
54
Procured
54
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
20563.00
Meter
Length Laid
20560.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
7 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Bidhuna | Purwa Pitaram | 420265 | Muggpur | 79 | 4 | 5% | Work In Progress | Not Certified |
| 2 | Auraiya | Bidhuna | Barahar | 420267 | Sohni | 56 | 12 | 21% | Work In Progress | Not Certified |
| 3 | Auraiya | Achhalda | Chandaia | 420431 | Chandaia | 221 | 221 | 100% | Har Ghar Jal | Not Certified |
| 4 | Auraiya | Achhalda | Chandaia | 420432 | Purwa Bhara Mal | 163 | 163 | 100% | Har Ghar Jal | Not Certified |
| 5 | Auraiya | Achhalda | Aili | 420433 | Aili | 205 | 205 | 100% | Har Ghar Jal | Certified |
| 6 | Auraiya | Achhalda | Aili | 420434 | Balkhandpur | 97 | 97 | 100% | Har Ghar Jal | Not Certified |
| 7 | Auraiya | Achhalda | Tilakpur Sarmedi | 420435 | Tilakpur Sakheri | 197 | 190 | 96% | Work In Progress | Not Certified |