Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Auraiya GVPR 20088691 Ali & Tilakpur sarmai PWS 664.84 454.61 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
7 2 2 2 2 1 1 0 54 54 Yes 0 NA No 20563.00 20560.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Auraiya Bidhuna Purwa Pitaram 420265 Muggpur 79 4 5 Work In Progress Not Certified
2 Auraiya Bidhuna Barahar 420267 Sohni 56 12 21 Work In Progress Not Certified
3 Auraiya Achhalda Chandaia 420431 Chandaia 221 221 100 Har Gar Jal Not Certified
4 Auraiya Achhalda Chandaia 420432 Purwa Bhara Mal 163 163 100 Har Gar Jal Not Certified
5 Auraiya Achhalda Aili 420433 Aili 205 205 100 Har Gar Jal Not Certified
6 Auraiya Achhalda Aili 420434 Balkhandpur 97 97 100 Har Gar Jal Not Certified
7 Auraiya Achhalda Tilakpur Sarmedi 420435 Tilakpur Sakheri 197 190 96 Work In Progress Not Certified