Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Auraiya | GVPR | 20088692 | Bhedpur & Nagla baish | 774.85 | 597.93 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 2 | 2 | 2 | 2 | 1 | 0 | 1 | 40 | 40 | Yes | 0 | NA | No | 19957.00 | 19957.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Airwakatra | Nagla Bais | 420212 | Nagla Bais | 261 | 256 | 98 | Work In Progress | Not Certified |
| 2 | Auraiya | Airwakatra | Nagla Bais | 420213 | Beljhali | 155 | 151 | 97 | Work In Progress | Not Certified |
| 3 | Auraiya | Airwakatra | Bhedpur | 420216 | Bhedpur | 604 | 604 | 100 | Har Gar Jal | Not Certified |
| 4 | Auraiya | Airwakatra | Bhedpur | 420217 | Jaswantpur | 46 | 46 | 100 | Har Gar Jal | Not Certified |
| 5 | Auraiya | Airwakatra | Patna Airwa | 420231 | Umredhi | 195 | 190 | 97 | Work In Progress | Not Certified |