Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20088736 | KASIYANW GRAM PANCHAYAT WATER SUPPLY SCHEME | 294.54 | 61.86 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 20 | 20 | NA | 0 | NA | No | 17187.00 | 15158.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Ramnagar | Kasiyanw | 470770 | Jalaluddinpur | 35 | 28 | 80 | Work In Progress | Not Certified |
| 2 | Jaunpur | Ramnagar | Kasiyanw | 470771 | Kasiyanw | 265 | 194 | 73 | Work In Progress | Not Certified |
| 3 | Jaunpur | Ramnagar | Kasiyanw | 470772 | Jirakpur | 12 | 11 | 92 | Work In Progress | Not Certified |