Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | VSA | 20088787 | HALLA & HARIHARPUR REORGANISATION W/S SCHEME (VSA) | 428.92 | 143.84 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | NA | 13 | NA | No | 29850.00 | 15984.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Manihari | Halla | 471843 | Halla | 238 | 167 | 70 | Work In Progress | Not Certified |
| 2 | Ghazipur | Manihari | Halla | 471844 | Jangipur | 117 | 92 | 79 | Work In Progress | Not Certified |
| 3 | Ghazipur | Manihari | Hariharpur | 471850 | Hariharpur | 455 | 390 | 86 | Work In Progress | Not Certified |