Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Larsen & Toubro Ltd | 20088795 | SEMARACHAK FAIZ W/S SCHEME | 234.00 | 58.60 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Ghazipur | Semarachak Faiz | 472881 | Semarachak Faiz | 162 | 159 | 98 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Ghazipur | Semarachak Faiz | 472882 | Semara Buzurg | 10 | 1 | 10 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Ghazipur | Semarachak Faiz | 472883 | Jalalabad | 3 | 1 | 33 | Work In Progress | Not Certified | Not Verified |
4 | Ghazipur | Ghazipur | Semarachak Faiz | 472884 | Chak Khazigi | 79 | 71 | 90 | Work In Progress | Not Certified | Not Verified |
5 | Ghazipur | Ghazipur | Semarachak Faiz | 472885 | Shekhpur | 99 | 34 | 34 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 0 | 0 | 1 | 1 | 0 | 14 | 14 | NA | 0 | NA | No | 8360.00 | 680.00 |