Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Prayagraj | Larsen & Toubro Ltd | 20088879 | DHOLI WATER SUPPLY SCHEME | 290.42 | 132.18 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Prayagraj | Saidabad | Dholi | 433644 | Dholi | 127 | 104 | 82 | Work In Progress | Not Certified | Not Verified |
2 | Prayagraj | Saidabad | Dholi | 433645 | Goaharpur Ta. Jalalpur | 82 | 71 | 87 | Work In Progress | Not Certified | Not Verified |
3 | Prayagraj | Saidabad | Dholi | 433646 | Saidaha Jalalpur | 118 | 96 | 81 | Work In Progress | Not Certified | Not Verified |
4 | Prayagraj | Saidabad | Dholi | 433647 | Muhiuddinpur | 103 | 99 | 96 | Work In Progress | Not Certified | Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | NA | 10 | NA | No | 25614.00 | 25600.00 |