Scheme Details
DISTRICT
Shravasti
AGENCY
GA INFRA-VPL
SCHEME ID
20088918
SCHEME NAME
BELHA RAGHAV
ESTIMATED COST
284.15
EXPENDITURE
122.59
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11993.00
Meter
Length Laid
9693.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shravasti | Ekona | Belha Raghav | 443483 | Belha Radha | 409 | 407 | 100% | Work In Progress | Not Certified |