Scheme Details
DISTRICT
Ghazipur
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20088980
SCHEME NAME
SHAHPUR SOMMAR RAI W/S SCHEME
ESTIMATED COST
203.75
EXPENDITURE
192.74
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
11
Procured
11
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8402.00
Meter
Length Laid
6898.00
Meter
Scheme Assigned Villages
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Jakhania | SHAHPUR SONAMRAI | 471479 | SALEMPUR | 10 | 10 | 100% | Har Ghar Jal | Not Certified |
| 2 | Ghazipur | Jakhania | SHAHPUR SONAMRAI | 471480 | SHAHPUR BAHOR RAI | 89 | 84 | 94% | Work In Progress | Not Certified |
| 3 | Ghazipur | Jakhania | SHAHPUR SONAMRAI | 471481 | Somar Rai | 86 | 85 | 99% | Work In Progress | Not Certified |
| 4 | Ghazipur | Jakhania | SHAHPUR SONAMRAI | 678280 | Gaura Khurd | 4 | 1 | 25% | Work In Progress | Not Certified |