Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Larsen & Toubro Ltd | 20089021 | DILIPCHANDPUR WATER SUPPLY SCHEME | 174.76 | 41.73 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | 0 | NA | 10 | NA | No | 9197.00 | 1140.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Handiya | Dilipchandpur | 433727 | Dilipchandpur | 143 | 117 | 82 | Work In Progress | Not Certified | 
| 2 | Prayagraj | Handiya | Dilipchandpur | 433728 | Hemapur | 43 | 20 | 47 | Work In Progress | Not Certified | 
| 3 | Prayagraj | Handiya | Dilipchandpur | 433729 | Dihakhas | 40 | 21 | 52 | Work In Progress | Not Certified | 
| 4 | Prayagraj | Handiya | Dilipchandpur | 433730 | Kashinathpur | 57 | 33 | 58 | Work In Progress | Not Certified | 
| 5 | Prayagraj | Dhanoopur | Kangapur | 433731 | HOLAPUR | 159 | 133 | 84 | Work In Progress | Not Certified |