Scheme Details
DISTRICT
Shahjahanpur
AGENCY
NCC Ltd.
SCHEME ID
20089065
SCHEME NAME
FATEHPUR BUJURG & BANDHA MULTI GP WSS
ESTIMATED COST
488.37
EXPENDITURE
282.82
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
8
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
28
Procured
36
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
32343.00
Meter
Length Laid
32101.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
8 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | Tilhar | Bandha | 406745 | Bandha | 190 | 188 | 99% | Work In Progress | Not Certified |
| 2 | Shahjahanpur | Tilhar | Bandha | 406746 | Tai | 133 | 133 | 100% | Har Ghar Jal | Not Certified |
| 3 | Shahjahanpur | Tilhar | Bandha | 406747 | Bandhi Chak | 142 | 142 | 100% | Har Ghar Jal | Not Certified |
| 4 | Shahjahanpur | Tilhar | Fatehpur Buzurg | 406791 | Fatehpur Buzurg | 103 | 92 | 89% | Work In Progress | Not Certified |
| 5 | Shahjahanpur | Tilhar | Fatehpur Buzurg | 406792 | Rajakpur | 81 | 81 | 100% | Har Ghar Jal | Not Certified |
| 6 | Shahjahanpur | Tilhar | Fatehpur Buzurg | 406793 | Diya Khera | 67 | 65 | 97% | Work In Progress | Not Certified |
| 7 | Shahjahanpur | Tilhar | Fatehpur Buzurg | 406794 | Fattepur Gaisara | 69 | 69 | 100% | Har Ghar Jal | Not Certified |
| 8 | Shahjahanpur | Tilhar | Fatehpur Buzurg | 680856 | Meer Meerapur | 3 | 3 | 100% | Har Ghar Jal | Not Certified |