Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Shahjahanpur
AGENCY NCC Ltd.
SCHEME ID 20089108
SCHEME NAME HASUA ZAGU GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST 262.06
EXPENDITURE 148.72
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 15
Procured 15 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 11097.00 Meter
Length Laid 10989.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Shahjahanpur Kanth Bsbauri Eo Marena 407136 Baburi Ilaqa Marena 251 248 99% Work In Progress Not Certified
2 Shahjahanpur Dadrol Hasua Zagu 407246 Hasua Jajoo 200 194 97% Work In Progress Not Certified