Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Vindhya-GAJA (JV) | 20089160 | Kasampur Kirparam Water Supply Scheme | 283.21 | 175.85 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 23 | Yes | 0 | NA | No | 7171.00 | 6760.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Mo. Purdewal | Kasampur Kirparam | 386091 | Kasampur Kirparam | 371 | 371 | 100 | Har Gar Jal | Not Certified |
| 2 | Bijnor | Mo. Purdewal | Kasampur Kirparam | 386092 | Aspur | 221 | 146 | 66 | Work In Progress | Not Certified |
| 3 | Bijnor | Mo. Purdewal | Kasampur Kirparam | 386093 | Rawanpur | 76 | 73 | 96 | Work In Progress | Not Certified |