Scheme Details
DISTRICT
Jaunpur
AGENCY
Welspun Kaveri Infraprojects JV
SCHEME ID
20089188
SCHEME NAME
Raipur
ESTIMATED COST
307.42
EXPENDITURE
145.62
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
37
Procured
37
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18714.00
Meter
Length Laid
10000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Rampur | RAI PUR | 471006 | ARAJI MAFI | 26 | 10 | 38% | Work In Progress | Not Certified |
| 2 | Jaunpur | Rampur | RAI PUR | 471007 | RAIPUR | 594 | 547 | 92% | Work In Progress | Not Certified |