Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Welspun Kaveri Infraprojects JV | 20089192 | Kaweli | 479.30 | 165.87 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 37 | 37 | NA | 0 | NA | No | 27820.00 | 27820.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Badlapur | Kaweli | 468709 | Kaweli | 283 | 277 | 98 | Work In Progress | Not Certified |
| 2 | Jaunpur | Badlapur | Sirkina | 468711 | Sirkina | 189 | 109 | 58 | Work In Progress | Not Certified |
| 3 | Jaunpur | Badlapur | Sirkina | 468712 | Setapur | 79 | 45 | 57 | Work In Progress | Not Certified |
| 4 | Jaunpur | Badlapur | Sirkina | 468713 | Sarai Chandi | 37 | 20 | 54 | Work In Progress | Not Certified |
| 5 | Jaunpur | Badlapur | Bahur | 468828 | Bahur | 161 | 122 | 76 | Work In Progress | Not Certified |