Scheme Details
DISTRICT
Fatehpur
AGENCY
Power Mech Projects Ltd
SCHEME ID
20089317
SCHEME NAME
GOVINDPUR BILARI
ESTIMATED COST
303.15
EXPENDITURE
155.09
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8873.00
Meter
Length Laid
8866.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Amauli | Govindpur Bilari | 427528 | Govindpur Bilari | 256 | 255 | 100% | Work In Progress | Not Certified |
| 2 | Fatehpur | Amauli | Govindpur Bilari | 427529 | Gangpur | 175 | 175 | 100% | Har Ghar Jal | Not Certified |