Scheme Details
DISTRICT
Auraiya
AGENCY
GVPR
SCHEME ID
20089638
SCHEME NAME
Ekgara bidhuna PWS
ESTIMATED COST
393.58
EXPENDITURE
314.52
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12998.00
Meter
Length Laid
12987.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Airwakatra | Ekghara Bidhuna | 420249 | Ekghara Bidhuna | 235 | 235 | 100% | Har Ghar Jal | Certified |
| 2 | Auraiya | Bidhuna | Nandpur | 420255 | Nandpur | 117 | 109 | 93% | Work In Progress | Not Certified |
| 3 | Auraiya | Bidhuna | Nandpur | 420256 | Kunwarpur | 71 | 67 | 94% | Work In Progress | Not Certified |
| 4 | Auraiya | Bidhuna | Nandpur | 420257 | Ram Nagaria | 109 | 109 | 100% | Har Ghar Jal | Not Certified |