Scheme Details
DISTRICT
Pratapgarh
AGENCY
Power Mech Projects Ltd
SCHEME ID
20089695
SCHEME NAME
Kabirpur Water Supply Scheme
ESTIMATED COST
196.42
EXPENDITURE
175.02
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11610.00
Meter
Length Laid
10922.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pratapgarh | Aaspur Devsara | Kabirpur | 430417 | Bikram Patti | 68 | 68 | 100% | Har Ghar Jal | Certified |
| 2 | Pratapgarh | Aaspur Devsara | Kabirpur | 430418 | Kabirpur | 134 | 134 | 100% | Har Ghar Jal | Certified |
| 3 | Pratapgarh | Aaspur Devsara | Kabirpur | 430419 | Semara Deeh | 72 | 72 | 100% | Har Ghar Jal | Certified |