| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Gonda | Larsen & Toubro Ltd | 20089854 | Naraicha_Sohila Water Supply Scheme | 416.25 | 140.72 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 25 | 25 | Yes | 0 | NA | No | 31942.49 | 0.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gonda | Chhapia | Sohila | 446140 | Sohila | 174 | 174 | 100 | Har Gar Jal | Not Certified | 
| 2 | Gonda | Chhapia | Sohila | 446141 | Bhikharipur | 76 | 71 | 93 | Work In Progress | Not Certified | 
| 3 | Gonda | Chhapia | Naraicha | 446181 | Saidanpr | 82 | 80 | 98 | Work In Progress | Not Certified | 
| 4 | Gonda | Chhapia | Naraicha | 446182 | Sherapur | 13 | 10 | 77 | Work In Progress | Not Certified | 
| 5 | Gonda | Chhapia | Naraicha | 446183 | Din Nagar | 141 | 139 | 99 | Work In Progress | Not Certified | 
| 6 | Gonda | Chhapia | Naraicha | 446184 | Naraicha | 225 | 220 | 98 | Work In Progress | Not Certified |