Scheme Details
DISTRICT
Gonda
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20089864
SCHEME NAME
CHARU Water Supply Scheme
ESTIMATED COST
344.10
EXPENDITURE
95.94
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
18
Procured
18
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13689.00
Meter
Length Laid
10.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gonda | Chhapia | CHARU | 446215 | VETWA | 172 | 168 | 98% | Work In Progress | Not Certified |
| 2 | Gonda | Chhapia | CHARU | 446216 | PARSA DULLA | 65 | 60 | 92% | Work In Progress | Not Certified |
| 3 | Gonda | Chhapia | CHARU | 446217 | CHARU | 290 | 285 | 98% | Work In Progress | Not Certified |