Scheme Details
DISTRICT
Raebareli
AGENCY
NCC Ltd.
SCHEME ID
20089929
SCHEME NAME
Dalmau Water Supply Scheme
ESTIMATED COST
622.83
EXPENDITURE
583.85
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
42
Procured
42
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
38848.00
Meter
Length Laid
37050.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Dalmau | Dalmau Mu. | 417334 | Dalmau Mu. | 1629 | 1595 | 98% | Work In Progress | Not Certified |