Scheme Details
DISTRICT
Ghazipur
AGENCY
VSA
SCHEME ID
20089933
SCHEME NAME
GOVINDPUR KIRAT REORGANISATION W/S SCHEME (VSA)
ESTIMATED COST
2780.45
EXPENDITURE
797.40
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
9
T/W Progress
Required
12
Boring Done
12
Air Compressor Done
12
O.P. Unit Done
12
OHT Progress
Required
5
Work Started
0
Work Completed
0
Solar Plant
Required
176
Procured
176
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
108234.00
Meter
Length Laid
105046.00
Meter
Scheme Assigned Villages
9 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Mardah | Govindpur Kirat | 472666 | Govindpur Kirat | 977 | 849 | 87% | Work In Progress | Not Certified |
| 2 | Ghazipur | Mardah | Govindpur Kirat | 472667 | Shakkapur | 39 | 1 | 3% | Work In Progress | Not Certified |
| 3 | Ghazipur | Mardah | Govindpur Kirat | 472668 | Dewapur | 13 | 1 | 8% | Work In Progress | Not Certified |
| 4 | Ghazipur | Mardah | Durkhushi | 472684 | Durkhushi | 895 | 851 | 95% | Work In Progress | Not Certified |
| 5 | Ghazipur | Mardah | Nasaratpur | 472686 | Nasaratpur | 585 | 351 | 60% | Work In Progress | Not Certified |
| 6 | Ghazipur | Mardah | Barahi | 472709 | Barahi | 578 | 555 | 96% | Work In Progress | Not Certified |
| 7 | Ghazipur | Mardah | Barahi | 472710 | Maliknathpur | 100 | 96 | 96% | Work In Progress | Not Certified |
| 8 | Ghazipur | Mardah | Harhari | 472763 | Harhari | 161 | 129 | 80% | Work In Progress | Not Certified |
| 9 | Ghazipur | Mardah | Harhari | 472764 | Shadhopur | 86 | 55 | 64% | Work In Progress | Not Certified |