Scheme Details
DISTRICT Raebareli
AGENCY NCC Ltd.
SCHEME ID 20090026
SCHEME NAME Chilaula Bhagriya Water Supply Scheme
ESTIMATED COST 351.11
EXPENDITURE 235.44
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 25
Procured 25 KW
Work Status NA
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 20091.00 Meter
Length Laid 19599.43 Meter

Scheme Assigned Villages

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Raebareli Sataon Chilaula Bhagariya 416795 Chilaula Bhagariya 407 399 98% Work In Progress Not Certified
2 Raebareli Sataon Chilaula Bhagariya 416796 Chak Godwa 29 26 90% Work In Progress Not Certified
3 Raebareli Sataon Chilaula Bhagariya 416797 Shahpur Singaria 79 77 97% Work In Progress Not Certified
4 Raebareli Sataon Chilaula Bhagariya 677997 Shahpur 10 6 60% Work In Progress Not Certified