Scheme Details
DISTRICT Gonda
AGENCY Larsen & Toubro Ltd
SCHEME ID 20090129
SCHEME NAME Devrahna_BHAWANIPUR KHURD Water Supply Scheme
ESTIMATED COST 309.00
EXPENDITURE 151.50
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 21
Procured 21 KW
Work Status No
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 16722.00 Meter
Length Laid 16700.00 Meter

Scheme Assigned Villages

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Gonda Rupaidih DEVRAHNA 444526 DEVRAHNA 172 168 98% Work In Progress Not Certified
2 Gonda Rupaidih Bhawanipur Khurd 444528 Bhawanipur Khurd 467 462 99% Work In Progress Not Certified