Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | VISHVARAJ | 20090333 | rampuria Sirsa+ 1 Multi GP water supply scheme | 417.37 | 231.31 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 27 | Yes | 0 | NA | No | 14397.00 | 14297.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Marori | Rura Ramnagar | 404665 | Rura Ramnagar | 226 | 88 | 39 | Work In Progress | Not Certified |
| 2 | Pilibhit | Marori | Rura Ramnagar | 404666 | Harkishanpur | 7 | 1 | 14 | Work In Progress | Not Certified |
| 3 | Pilibhit | Marori | Rura Ramnagar | 404667 | Araji Dahgala | 86 | 81 | 94 | Work In Progress | Not Certified |
| 4 | Pilibhit | Marori | Rampuria Sirsa | 404730 | Rampuria Sirsa | 376 | 338 | 90 | Work In Progress | Not Certified |
| 5 | Pilibhit | Marori | Rampuria Sirsa | 404731 | Araji Rampuria | 80 | 49 | 61 | Work In Progress | Not Certified |
| 6 | Pilibhit | Marori | Rampuria Sirsa | 404732 | Kundri Dahgala | 2 | 1 | 50 | Work In Progress | Not Certified |