Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Gonda | KLSR - RAYS (JV) | 20090354 | GOSAINPUR & BISUNPUR TEWARI W/S SCHEME | 434.03 | 142.98 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 30 | 30 | Yes | 0 | NA | No | 28901.00 | 17050.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gonda | Itia Thok | Bisunpur Tewari | 444685 | Bisunpur Tewari | 147 | 103 | 70 | Work In Progress | Not Certified | 
| 2 | Gonda | Itia Thok | Bisunpur Tewari | 444686 | Ram Gathiha | 158 | 138 | 87 | Work In Progress | Not Certified | 
| 3 | Gonda | Itia Thok | Gosainpur | 444687 | Gosainpur | 481 | 439 | 91 | Work In Progress | Not Certified |