Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Rampur
AGENCY SPML Infra
SCHEME ID 20090364
SCHEME NAME RAWANNA LALA URF BISHANPURI MV W/S SCHEME
ESTIMATED COST 174.44
EXPENDITURE 72.75
AUTOMATION STATUS
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 5
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 9
Procured 9 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 9840.00 Meter
Length Laid 9840.00 Meter

Scheme Assigned Villages

5 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Rampur Bilaspur Rawana Lala Urf Bishanpuri 389516 Rawana Lala Urf Bishanpuri 122 119 98% Work In Progress Not Certified
2 Rampur Bilaspur Rawana Lala Urf Bishanpuri 389518 Rawana Ghasi 22 20 91% Work In Progress Not Certified
3 Rampur Bilaspur Rawana Lala Urf Bishanpuri 389519 Mushrrafganj 60 55 92% Work In Progress Not Certified
4 Rampur Bilaspur Rawana Lala Urf Bishanpuri 389520 Ahamdabad 19 15 79% Work In Progress Not Certified
5 Rampur Bilaspur Rawana Lala Urf Bishanpuri 677680 RAWANA KANNU 1 1 100% Har Ghar Jal Not Certified