Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Rampur | OMIL-JWIL (JV) | 20090393 | PATTI KALYANPUR MV GP W/S SCHEME | 197.80 | 68.67 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 16 | 16 | NA | 0 | NA | No | 4760.00 | 4730.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Rampur | Chamraua | Patti Kalyanpur | 389874 | Patti Kalyanpur | 264 | 261 | 99 | Work In Progress | Not Certified | 
| 2 | Rampur | Chamraua | Patti Kalyanpur | 677688 | ABBAS NAGAR | 89 | 88 | 99 | Work In Progress | Not Certified |