Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Gonda | KLSR - RAYS (JV) | 20090429 | TEKRI & DEOGAON W/S SCHEME | 322.81 | 164.70 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 23 | 23 | No | 0 | NA | No | 21856.00 | 20560.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gonda | Chhapia | Teeker | 446219 | Domaipur | 57 | 15 | 26 | Work In Progress | Not Certified | 
| 2 | Gonda | Chhapia | Teeker | 446220 | Teeker | 187 | 160 | 86 | Work In Progress | Not Certified | 
| 3 | Gonda | Chhapia | Dev Gaon | 446221 | Dev Gaon | 211 | 150 | 71 | Work In Progress | Not Certified |