Scheme Details
DISTRICT
Gonda
AGENCY
KLSR - RAYS (JV)
SCHEME ID
20090436
SCHEME NAME
NARHARPUR & SEMRA BUJURG W/S SCHEME
ESTIMATED COST
366.13
EXPENDITURE
129.25
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
23
Procured
23
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
32346.00
Meter
Length Laid
21476.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gonda | Babhanjot | SEMRA BUJURG | 446117 | SEMRA BUZURG | 163 | 149 | 91% | Work In Progress | Not Certified |
| 2 | Gonda | Babhanjot | NARHARPUR | 446123 | NARHARPUR | 312 | 291 | 93% | Work In Progress | Not Certified |