Scheme Details
DISTRICT
Barabanki
AGENCY
Megha
SCHEME ID
20090456
SCHEME NAME
Aswa Water Supply Scheme
ESTIMATED COST
260.66
EXPENDITURE
106.81
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
16733.00
Meter
Length Laid
12775.00
Meter
Scheme Assigned Villages
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Puredalai | Aswa | 435685 | Aswa | 160 | 160 | 100% | Har Ghar Jal | Not Certified |
| 2 | Barabanki | Puredalai | Aswa | 435686 | Maila | 24 | 20 | 83% | Work In Progress | Not Certified |
| 3 | Barabanki | Puredalai | Aswa | 435687 | Lilar | 59 | 56 | 95% | Work In Progress | Not Certified |
| 4 | Barabanki | Puredalai | Aswa | 677522 | Kitubhi | 118 | 115 | 97% | Work In Progress | Not Certified |