Scheme Details
DISTRICT Pratapgarh
AGENCY JMC - Lakshmi (JV)
SCHEME ID 20090531
SCHEME NAME Tavankalpur & Pahadpur
ESTIMATED COST 616.24
EXPENDITURE 175.30
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 2
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 42
Procured 42 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 33688.00 Meter
Length Laid 17600.00 Meter

Scheme Assigned Villages

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Pratapgarh Gaura Tavankalpur 430755 Tavankalpur 441 441 100% Har Ghar Jal Not Certified
2 Pratapgarh Gaura Tavankalpur 430756 Sujanpur 99 91 92% Work In Progress Not Certified