Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Barabanki
AGENCY PNC-SPML-JV
SCHEME ID 20090563
SCHEME NAME Odaria & Pindsawa Water Supply Scheme
ESTIMATED COST 410.88
EXPENDITURE 214.71
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 30
Procured 30 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 18078.00 Meter
Length Laid 16345.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Barabanki Nindaura Odaria 434433 Odaria 424 419 99% Work In Progress Not Certified
2 Barabanki Nindaura Pindsawa 434450 Pindsawa 434 429 99% Work In Progress Not Certified