Scheme Details
DISTRICT
Basti
AGENCY
Megha
SCHEME ID
20090584
SCHEME NAME
SILWATIYA GP wss
ESTIMATED COST
121.19
EXPENDITURE
55.22
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
13
Procured
13
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
5414.00
Meter
Length Laid
5414.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Ramnagar | Silwatiya | 448797 | Silwatia | 97 | 96 | 99% | Work In Progress | Not Certified |
| 2 | Basti | Ramnagar | Silwatiya | 448801 | Bargadahi | 69 | 69 | 100% | Har Ghar Jal | Certified |