Scheme Details
DISTRICT
Bareilly
AGENCY
NCC Ltd.
SCHEME ID
20090594
SCHEME NAME
Haidarganj urf Alganj water supply scheme
ESTIMATED COST
586.00
EXPENDITURE
310.39
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
28
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18105.00
Meter
Length Laid
18000.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Majhgawan | Haidarganj Urf Aliganj | 403481 | Haidarganj Urf Aliganj | 1684 | 1683 | 100% | Work In Progress | Not Certified |
| 2 | Bareilly | Majhgawan | Haidarganj Urf Aliganj | 403482 | Rampura Khurd | 31 | 31 | 100% | Har Ghar Jal | Not Certified |