Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Barabanki | PNC-SPML-JV | 20090629 | Saraiya Modmitnagar Water Supply Scheme | 239.22 | 112.65 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | NA | 63 | NA | No | 12027.00 | 10250.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Fatehpur | Saraiya Modmitnagar | 434685 | Saraiya Modmitnagar | 92 | 92 | 100 | Har Gar Jal | Not Certified |
| 2 | Barabanki | Fatehpur | Saraiya Modmitnagar | 434686 | Saraiya Daljit | 86 | 84 | 98 | Work In Progress | Not Certified |
| 3 | Barabanki | Fatehpur | Saraiya Modmitnagar | 434687 | Pahla Saraiya | 88 | 84 | 95 | Work In Progress | Not Certified |
| 4 | Barabanki | Fatehpur | Saraiya Modmitnagar | 434688 | Saraiya Kuti | 95 | 94 | 99 | Work In Progress | Not Certified |
| 5 | Barabanki | Fatehpur | Saraiya Modmitnagar | 434689 | Deokaliya | 88 | 85 | 97 | Work In Progress | Not Certified |