Scheme Details
DISTRICT
Raebareli
AGENCY
NCC Ltd.
SCHEME ID
20090642
SCHEME NAME
Behi Khor Water Supply Scheme
ESTIMATED COST
383.25
EXPENDITURE
299.27
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
25
Procured
25
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
21707.00
Meter
Length Laid
18328.50
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Deenshah Gaura | Behi Khor | 417384 | Behi Khor | 520 | 520 | 100% | Har Ghar Jal | Not Certified |
| 2 | Raebareli | Deenshah Gaura | Behi Khor | 417385 | Serandajpur | 10 | 10 | 100% | Har Ghar Jal | Not Certified |