Scheme Details
DISTRICT
Varanasi
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20090697
SCHEME NAME
Zone 1 - Rauna Khurd_Barthauli Water Supply Scheme
ESTIMATED COST
421.82
EXPENDITURE
200.36
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
35
Procured
35
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
26676.00
Meter
Length Laid
26642.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Cholapur | Rauna Kala | 475865 | Rauna Kala | 400 | 363 | 91% | Work In Progress | Not Certified |
| 2 | Varanasi | Cholapur | Barthauli | 475875 | Bartholi | 163 | 136 | 83% | Work In Progress | Not Certified |
| 3 | Varanasi | Cholapur | Rauna Khurd | 475914 | Rauna Khurd | 793 | 705 | 89% | Work In Progress | Not Certified |