Scheme Details
DISTRICT
Raebareli
AGENCY
NCC Ltd.
SCHEME ID
20090846
SCHEME NAME
SUCHI Water Supply Scheme
ESTIMATED COST
482.59
EXPENDITURE
442.50
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
35
Procured
35
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
30995.00
Meter
Length Laid
30995.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Salon | Suchi | 417909 | Suchi | 1066 | 1029 | 97% | Work In Progress | Not Certified |