Scheme Details
DISTRICT
Varanasi
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20090880
SCHEME NAME
Prayagpur Zone 1_Burapur_Payagpur Water Supply Scheme
ESTIMATED COST
325.21
EXPENDITURE
139.79
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
25
Procured
25
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
21933.00
Meter
Length Laid
11205.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Arajiline | Burapur | 476407 | Burapur | 263 | 251 | 95% | Work In Progress | Not Certified |
| 2 | Varanasi | Arajiline | Todarpur | 476512 | Todarpur | 419 | 392 | 94% | Work In Progress | Not Certified |
| 3 | Varanasi | Arajiline | Payagpur | 476514 | Chak Maat Dai | 134 | 128 | 96% | Work In Progress | Not Certified |
| 4 | Varanasi | Arajiline | Payagpur | 476515 | Payagpur | 179 | 151 | 84% | Work In Progress | Not Certified |