Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Larsen & Toubro Ltd | 20090898 | Pindra Zone 2_Jamapur_Ajaipur Water Supply Scheme | 218.51 | 96.22 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 21 | 21 | Yes | 0 | NA | No | 7877.00 | 7658.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Pindara | Ajaipur | 475710 | Ajaipur | 220 | 220 | 100 | Har Gar Jal | Not Certified |
| 2 | Varanasi | Pindara | Jamapur | 475712 | Jamapur | 148 | 148 | 100 | Har Gar Jal | Not Certified |
| 3 | Varanasi | Pindara | Jamapur | 475713 | Lokapur | 54 | 39 | 72 | Work In Progress | Not Certified |