Scheme Details
DISTRICT
Varanasi
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20090945
SCHEME NAME
Mirzamurad Zone 1_Goar Water Supply Scheme
ESTIMATED COST
433.84
EXPENDITURE
158.28
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
20
Transformer Procured
Yes
Work Status
No
Distribution Line
Total Length
26920.00
Meter
Length Laid
26920.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Arajiline | Goar | 476444 | Goar | 1644 | 1203 | 73% | Work In Progress | Not Certified |
| 2 | Varanasi | Arajiline | Goar | 476445 | Madhokar Shahpur | 144 | 144 | 100% | Har Ghar Jal | Not Certified |
| 3 | Varanasi | Arajiline | Goar | 476446 | Hari Ram Pur | 2 | 2 | 100% | Har Ghar Jal | Not Certified |