Scheme Details
DISTRICT
Auraiya
AGENCY
GVPR
SCHEME ID
20091149
SCHEME NAME
Bailipur PWS
ESTIMATED COST
209.98
EXPENDITURE
175.70
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
4770.00
Meter
Length Laid
4990.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Achhalda | Bailipur | 420416 | Bailipur | 187 | 187 | 100% | Har Ghar Jal | Certified |