Scheme Details
DISTRICT
Auraiya
AGENCY
GVPR
SCHEME ID
20091154
SCHEME NAME
Babina PWS
ESTIMATED COST
121.34
EXPENDITURE
78.35
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
0
Work Started
0
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
25
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
3530.00
Meter
Length Laid
3530.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Bhagyanagar | Babina | 420758 | Babina | 250 | 238 | 95% | Work In Progress | Not Certified |