Scheme Details
DISTRICT
Auraiya
AGENCY
GVPR
SCHEME ID
20091160
SCHEME NAME
Chakshakatpur & chiktapur
ESTIMATED COST
407.89
EXPENDITURE
168.02
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13430.00
Meter
Length Laid
13425.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Ajitmal | Chak Sakatapur | 420602 | Chak Sakatapur | 142 | 132 | 93% | Work In Progress | Not Certified |
| 2 | Auraiya | Ajitmal | Chak Sakatapur | 420603 | Adampur | 151 | 146 | 97% | Work In Progress | Not Certified |
| 3 | Auraiya | Ajitmal | Chitkapur | 420604 | Chitkapur | 336 | 320 | 95% | Work In Progress | Not Certified |
| 4 | Auraiya | Ajitmal | Chitkapur | 420605 | Gazipur Bhawani Prasad | 59 | 59 | 100% | Har Ghar Jal | Not Certified |