Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Auraiya | GVPR | 20091160 | Chakshakatpur & chiktapur | 407.89 | 146.06 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 30 | 30 | Yes | 0 | NA | No | 13430.00 | 13425.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Ajitmal | Chak Sakatapur | 420602 | Chak Sakatapur | 142 | 132 | 93 | Work In Progress | Not Certified |
| 2 | Auraiya | Ajitmal | Chak Sakatapur | 420603 | Adampur | 151 | 146 | 97 | Work In Progress | Not Certified |
| 3 | Auraiya | Ajitmal | Chitkapur | 420604 | Chitkapur | 336 | 320 | 95 | Work In Progress | Not Certified |
| 4 | Auraiya | Ajitmal | Chitkapur | 420605 | Gazipur Bhawani Prasad | 59 | 59 | 100 | Har Gar Jal | Not Certified |