Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Pratapgarh | JMC - Lakshmi (JV) | 20091169 | Gajariya Water Supply Scheme | 274.85 | 111.99 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | NA | 15 | NA | No | 20157.00 | 20057.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pratapgarh | Patuti | Molanapur | 430366 | Molanapur | 207 | 205 | 99 | Work In Progress | Not Certified | 
| 2 | Pratapgarh | Patuti | Molanapur | 430367 | Godhu Patti | 52 | 50 | 96 | Work In Progress | Not Certified | 
| 3 | Pratapgarh | Patuti | Gajariya | 430381 | Gajariya | 260 | 259 | 100 | Work In Progress | Not Certified |