Scheme Details
DISTRICT
Auraiya
AGENCY
GVPR
SCHEME ID
20091180
SCHEME NAME
Bharrapur PWS
ESTIMATED COST
243.38
EXPENDITURE
139.11
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
5850.00
Meter
Length Laid
5841.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Bhagyanagar | Bharrapur | 420678 | Bharrapur | 237 | 225 | 95% | Work In Progress | Not Certified |
| 2 | Auraiya | Bhagyanagar | Bharrapur | 420679 | Adhasi | 175 | 164 | 94% | Work In Progress | Not Certified |