Scheme Details
DISTRICT
Ghazipur
AGENCY
HFCL- JWIL (JV)
SCHEME ID
20091411
SCHEME NAME
SHAKAPUR W/S SCHEME (HFCL)
ESTIMATED COST
239.49
EXPENDITURE
45.46
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
0
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
15
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9673.00
Meter
Length Laid
0.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Varachavar | Shakapur | 473421 | Shakapur | 330 | 242 | 73% | Work In Progress | Not Certified |